Adequate Progress Determination


Adequate Progress Determination : A written determination issued by FEMA to the Chief Executive Officer of a community that has provided sufficient information for FEMA to determine that substantial completion of a flood protection system has been effected because: (1) 100 percent of the total financial project cost of the completed flood protection system has been authorized; (2) at least 60 percent of the total financial project cost of the completed flood protection system has been appropriated; (3) at least 50 percent of the total financial project cost of the completed flood protection system has been expended; (4) all critical features of the flood protection system, as identified by FEMA, are under construction, and each critical feature is 50 percent completed as measured by the actual expenditure of the estimated construction budget funds; and (5) The community has not been responsible for any delay in the completion of the system